Construction of Road Dike aling Mag-asawang Tubig River, Sampaloc Section, Barangay Sto. Niño, Naujan, Oriental Mindoro
Location
Naujan, Oriental Mindoro
MIMAROPA Region
ZIP: 5204
13.253384, 121.188722
Project Cost
₱250M
₱247,496,440.5
Project Timeline
Start Date
March 08, 2024
Fri, Mar 08, 2024
Actual Start
March 08, 2024
Fri, Mar 08, 2024
Target Completion
August 14, 2024
Wed, Aug 14, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project