Construction of Flood Mitigation Structure along Mananga River (Upper Side), Talisay City, Cebu
Location
City of Talisay, Cebu
Central Visayas
ZIP: 6045
10.268650, 123.828580
Project Cost
₱140M
₱135,100,000.0
Project Timeline
Start Date
April 17, 2022
Sun, Apr 17, 2022
Actual Start
April 17, 2022
Sun, Apr 17, 2022
Target Completion
December 14, 2022
Wed, Dec 14, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates