Construction of Flood Mitigation Structure and Drainage System of Cantomimbo Flood Control, Balilihan, Bohol
Location
Cantomimbo, Balilihan, Bohol
Central Visayas
ZIP: 6342
9.766670, 123.986940
Project Cost
₱4.9M
₱4,885,000.0
Project Timeline
Start Date
February 15, 2023
Wed, Feb 15, 2023
Actual Start
February 15, 2023
Wed, Feb 15, 2023
Target Completion
April 24, 2023
Mon, Apr 24, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor