Flood Control Infrastructure
Main Portal
Completed
Construction of Flood Control Structure along Guinsay River, Danao, Cebu
P00721770VS
Location
Guinsay, Danao City, Cebu
Central Visayas
ZIP: 6004
10.540826, 124.024651
Project Cost
₱77M
₱77,077,770.77
Project Timeline
Start Date
March 29, 2023
Wed, Mar 29, 2023
Actual Start
March 29, 2023
Wed, Mar 29, 2023
Target Completion
December 23, 2023
Sat, Dec 23, 2023
Project Organizations
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
DPWH