Construction of Flood Control Structure along Jagobiao Creek, Barangay Casili to Barangay Sacsac, Phase II, Consolacion, Cebu
Location
Casili, Consolacion, Cebu
Central Visayas
ZIP: 6001
10.371373, 123.942593
Project Cost
₱140M
₱144,699,797.6
Project Timeline
Start Date
February 15, 2024
Thu, Feb 15, 2024
Actual Start
February 15, 2024
Thu, Feb 15, 2024
Target Completion
October 27, 2024
Sun, Oct 27, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor