Construction of Revetment Wall at Sitio Kanduong - Sitio Lawaan, Barangay Bala, Moalboal, Cebu
Location
Bala, Moalboal, Cebu
Central Visayas
ZIP: 6032
10.007425, 123.414573
Project Cost
₱58M
₱57,894,463.74
Project Timeline
Start Date
March 11, 2024
Mon, Mar 11, 2024
Actual Start
March 11, 2024
Mon, Mar 11, 2024
Target Completion
September 23, 2024
Mon, Sep 23, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor