Construction of Flood Control along Mananga River (Right Side) at Sitio Tigib, Barangay Lagtang, Talisay City, Cebu (Package 3)
Location
Lagtang, City of Talisay, Cebu
Central Visayas
ZIP: 6045
10.276748, 123.825558
Project Cost
₱140M
₱144,750,000.0
Project Timeline
Start Date
February 19, 2024
Mon, Feb 19, 2024
Actual Start
February 19, 2024
Mon, Feb 19, 2024
Target Completion
January 09, 2025
Thu, Jan 09, 2025
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close