Construction of Concrete Revetment, Upper Sinawal Bridge, Sinawal River, General Santos City
Location
Sinawal, City of General Santos, South Cotabato
SOCCSKSARGEN
ZIP: 9500
6.130222, 125.110575
Project Cost
₱51M
₱51,144,998.16
Project Timeline
Start Date
February 20, 2023
Mon, Feb 20, 2023
Actual Start
February 20, 2023
Mon, Feb 20, 2023
Target Completion
August 26, 2023
Sat, Aug 26, 2023
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1