Construction of Revetment Wall along Jaro River, Brgy. San Isidro, Jaro, Iloilo City
Location
San Isidro, City of Iloilo, Iloilo
Western Visayas
ZIP: 5000
10.834760, 122.549100
Project Cost
₱96M
₱95,504,856.0
Project Timeline
Start Date
February 20, 2022
Sun, Feb 20, 2022
Actual Start
February 20, 2022
Sun, Feb 20, 2022
Target Completion
April 04, 2023
Tue, Apr 04, 2023
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor