Construction of Molo Creek Flood Control, Alabel, Sarangani
Location
Alabel, Sarangani
SOCCSKSARGEN
ZIP: 9516
6.106250, 125.283860
Project Cost
₱49M
₱48,889,616.12
              
                
              
              Project Timeline
            
            Start Date
February 12, 2024
Mon, Feb 12, 2024
Actual Start
February 12, 2024
Mon, Feb 12, 2024
Target Completion
July 28, 2024
Sun, Jul 28, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
                
                  
                