Construction of Maligang River Control, Kiamba, Sarangani
Location
Maligang, Kiamba, Sarangani
SOCCSKSARGEN
ZIP: 9514
5.933200, 124.730917
Project Cost
₱53M
₱52,675,000.0
Project Timeline
Start Date
May 29, 2024
Wed, May 29, 2024
Actual Start
May 29, 2024
Wed, May 29, 2024
Target Completion
November 24, 2024
Sun, Nov 24, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close