Construction of Flood Control Structure along Jalaur River in Calinog, Iloilo
Location
Calinog, Iloilo
Western Visayas
ZIP: 5040
11.126380, 122.528200
Project Cost
₱34M
₱34,299,712.0
Project Timeline
Start Date
February 09, 2022
Wed, Feb 09, 2022
Actual Start
February 09, 2022
Wed, Feb 09, 2022
Target Completion
July 15, 2022
Fri, Jul 15, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor