Construction of Flood Control Structure of Sicaba River (Right Side - Downstream) along Bacolod North Rd, Cadiz City, Negros Occidental
Location
Sicaba, City of Cadiz, Negros Occidental
Western Visayas
ZIP: 6121
10.956670, 123.200300
Project Cost
₱39M
₱39,089,218.0
Project Timeline
Start Date
March 29, 2022
Tue, Mar 29, 2022
Actual Start
March 29, 2022
Tue, Mar 29, 2022
Target Completion
December 17, 2022
Sat, Dec 17, 2022
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor