Construction of Revetment with Floodwall in Banago Creek, Phase 3, Bacolod City
Location
Banago, City of Bacolod, Negros Occidental
Western Visayas
ZIP: 6100
10.705340, 122.959900
Project Cost
₱59M
₱58,857,280.0
Project Timeline
Start Date
February 28, 2022
Mon, Feb 28, 2022
Actual Start
February 28, 2022
Mon, Feb 28, 2022
Target Completion
May 14, 2023
Sun, May 14, 2023
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor