Flood Control Infrastructure
Main Portal
Completed
Construction of Seawall, Brgy San Roque, Barotac Viejo, Iloilo
P00633217VS
Location
San Roque, Barotac Viejo, Iloilo
Western Visayas
ZIP: 5018
11.024920, 122.863100
Project Cost
₱50M
₱49,500,000.0
Project Timeline
Start Date
March 23, 2022
Wed, Mar 23, 2022
Actual Start
March 23, 2022
Wed, Mar 23, 2022
Target Completion
April 16, 2023
Sun, Apr 16, 2023
Project Organizations
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
DPWH