Construction of Flood Control Structures along Cangaranan River at Valderrama Bridge, Abutment B, Upstream, Valderrama, Antique
Location
Valderrama, Antique
Western Visayas
ZIP: 5715
11.011220, 122.131600
Project Cost
₱49M
₱49,000,000.0
Project Timeline
Start Date
February 06, 2022
Sun, Feb 06, 2022
Actual Start
February 06, 2022
Sun, Feb 06, 2022
Target Completion
August 25, 2022
Thu, Aug 25, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor