Construction of Flood Control System in Baragnay Cabalagnan, Nueva Valencia, Guimaras
Location
Cabalagnan, Nueva Valencia, Guimaras
Western Visayas
ZIP: 5046
10.416630, 122.549500
Project Cost
₱58M
₱57,868,774.0
Project Timeline
Start Date
February 16, 2023
Thu, Feb 16, 2023
Actual Start
February 16, 2023
Thu, Feb 16, 2023
Target Completion
October 01, 2023
Sun, Oct 01, 2023
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor