Construction of Flood Mitigation Structure along Tibsok River, Municipality of San Enrique, Negros Occidental
Location
San Enrique, Negros Occidental
Western Visayas
ZIP: 6104
10.409400, 122.852200
Project Cost
₱29M
₱29,047,199.0
Project Timeline
Start Date
April 10, 2023
Mon, Apr 10, 2023
Actual Start
April 10, 2023
Mon, Apr 10, 2023
Target Completion
November 14, 2023
Tue, Nov 14, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project