Construction of Flood Control/Slope Protection along Tigum River, Maasin, Iloilo
Location
Maasin, Iloilo
Western Visayas
ZIP: 5030
10.883880, 122.471200
Project Cost
₱20M
₱19,599,435.0
Project Timeline
Start Date
February 12, 2023
Sun, Feb 12, 2023
Actual Start
February 12, 2023
Sun, Feb 12, 2023
Target Completion
August 24, 2023
Thu, Aug 24, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor