Construction of Flood Mitigation Structure along Kapalong-Talaingod-Valencia Road (Bonacao Stream - Bonacao Bridge, Tributary to Pulangui River), Brgy. Bonacao, Sta. 0+200 - Sta. 0+400 (BS), San Fernando, Bukidnon
Location
Bonacao, San Fernando, Bukidnon
Northern Mindanao
ZIP: 8716
7.800405, 125.393616
Project Cost
₱49M
₱48,999,994.29
Project Timeline
Start Date
January 27, 2022
Thu, Jan 27, 2022
Actual Start
January 27, 2022
Thu, Jan 27, 2022
Target Completion
October 25, 2022
Tue, Oct 25, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1