Construction of Flood Mitigation Structure, Purok 4 and Purok 8, Barangay Linabo, Sta. 0 + 000 - Sta. 0 + 207 (BS), Malaybalay City, Bukidnon
Location
Linabo, City of Malaybalay, Bukidnon
Northern Mindanao
ZIP: 8700
8.065304, 125.180769
Project Cost
₱96M
₱96,499,999.62
Project Timeline
Start Date
March 12, 2023
Sun, Mar 12, 2023
Actual Start
March 12, 2023
Sun, Mar 12, 2023
Target Completion
March 04, 2024
Mon, Mar 04, 2024
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close