Construction of River Control along Lumad Bridge, Barangay Lumad, Mambajao, Camiguin
Location
Mambajao, Camiguin
Northern Mindanao
ZIP: 9100
9.241025, 124.701313
Project Cost
₱49M
₱48,913,540.2
              
                
              
              Project Timeline
            
            Start Date
February 26, 2023
Sun, Feb 26, 2023
Actual Start
February 26, 2023
Sun, Feb 26, 2023
Target Completion
October 23, 2023
Mon, Oct 23, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
                
                  
                