Construction of Flood Mitigation Structure along Mandulog River at Digkilaan Bridge, Iligan City
Location
Digkilaan, City of Iligan, Lanao Del Norte
Northern Mindanao
ZIP: 9200
8.252990, 124.316586
Project Cost
₱77M
₱77,198,185.6
Project Timeline
Start Date
March 18, 2024
Mon, Mar 18, 2024
Actual Start
March 18, 2024
Mon, Mar 18, 2024
Target Completion
September 19, 2024
Thu, Sep 19, 2024
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...