Construction of Flood Control Structure, Barangay Dulong Bayan, San Jose Del Monte City, Bulacan
Location
Dulong Bayan, City of San Jose Del Monte, Bulacan
Central Luzon
ZIP: 3023
14.832220, 121.037220
Project Cost
₱44M
₱44,098,986.56
Project Timeline
Start Date
March 30, 2022
Wed, Mar 30, 2022
Actual Start
March 30, 2022
Wed, Mar 30, 2022
Target Completion
March 18, 2023
Sat, Mar 18, 2023
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor