Construction of San Joaqin Shoreline Protection including access road, San Joaqin, Iloilo
Location
San Joaquin, Iloilo
Western Visayas
ZIP: 5020
10.582630, 122.116500
Project Cost
₱29M
₱29,096,771.0
Project Timeline
Start Date
February 28, 2024
Wed, Feb 28, 2024
Actual Start
February 28, 2024
Wed, Feb 28, 2024
Target Completion
October 04, 2024
Fri, Oct 04, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...