Construction of Flood Control Structure at Ermitaño Creek, Brgy. Addition Hills, San Juan City
Location
City of San Juan
NCR
ZIP: 1500
14.596068, 121.040280
Project Cost
₱44M
₱44,096,995.9
Project Timeline
Start Date
March 21, 2023
Tue, Mar 21, 2023
Actual Start
March 21, 2023
Tue, Mar 21, 2023
Target Completion
February 11, 2024
Sun, Feb 11, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close