Construction of Revetment near Salvador Bridge (Upstream Side), Barangay San Isidro, Parañaque City, Metro Manila
Location
City of Parañaque
NCR
ZIP: 1744
14.475226, 121.002172
Project Cost
₱49M
₱48,999,076.1
Project Timeline
Start Date
May 22, 2023
Mon, May 22, 2023
Actual Start
May 22, 2023
Mon, May 22, 2023
Target Completion
March 16, 2024
Sat, Mar 16, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor