Construction of Flood Control Structure (Pumping Station) at Bagumbayan River including Upgrading of Drainage Outfall/Laterals (Phase 2), Barangay Bagumbayan, Taguig City
Location
City of Taguig
NCR
ZIP: 1717
14.466598, 121.057793
Project Cost
₱89M
₱88,875,980.92
Project Timeline
Start Date
October 08, 2023
Sun, Oct 08, 2023
Actual Start
October 08, 2023
Sun, Oct 08, 2023
Target Completion
June 03, 2024
Mon, Jun 03, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates