Construction of Flood Control Wall along the Banks of Creeks, Brgy. 172, Caloocan City
Location
Barangay 176, City of Caloocan
NCR
ZIP: 1124
14.745360, 121.042398
Project Cost
₱90M
₱89,748,679.99
Project Timeline
Start Date
February 20, 2023
Mon, Feb 20, 2023
Actual Start
February 20, 2023
Mon, Feb 20, 2023
Target Completion
December 18, 2023
Mon, Dec 18, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor