Project Cost
₱75M
₱74,700,405.94
Project Timeline
Start Date
March 08, 2023
Wed, Mar 08, 2023
Actual Start
March 08, 2023
Wed, Mar 08, 2023
Target Completion
March 30, 2024
Sat, Mar 30, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor