Construction of Flood Control Structure along Laguna de Bay, Barangay Putatan, Muntinlupa City
Location
Putatan, City of Muntinlupa
NCR
ZIP: 1770
14.400642, 121.052231
Project Cost
₱92M
₱91,568,484.81
Project Timeline
Start Date
February 16, 2022
Wed, Feb 16, 2022
Actual Start
February 16, 2022
Wed, Feb 16, 2022
Target Completion
August 24, 2022
Wed, Aug 24, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor