Rehabilitation of Flood Mitigation Structure, Mahabang Ilog Creek at Barangay Maybunga, Pasig City
Location
Maybunga, City of Pasig
NCR
ZIP: 1607
14.574356, 121.094659
Project Cost
₱4.6M
₱4,645,985.37
Project Timeline
Start Date
February 05, 2023
Sun, Feb 05, 2023
Actual Start
February 05, 2023
Sun, Feb 05, 2023
Target Completion
July 04, 2023
Tue, Jul 04, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor