Construction of Flood Control Wall along Camarin Creek (Right Side) Brgy. 178 and 180, Sta. 0+000 to Sta. 0+223, Caloocan City
Location
Barangay 178, City of Caloocan
NCR
ZIP: 1438
14.762058, 121.062214
Project Cost
₱48M
₱47,842,662.41
Project Timeline
Start Date
June 06, 2023
Tue, Jun 06, 2023
Actual Start
June 06, 2023
Tue, Jun 06, 2023
Target Completion
November 05, 2023
Sun, Nov 05, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project