Construction of Flood Control Structure along Dicayo River (Downstream), Barangay Dos, Katipunan, Zamboanga del Norte (Package 1)
Location
Katipunan, Zamboanga Del Norte
Zamboanga Peninsula
ZIP: 7000
8.506240, 123.298710
Project Cost
₱40M
₱39,708,089.93
Project Timeline
Start Date
February 09, 2022
Wed, Feb 09, 2022
Actual Start
February 09, 2022
Wed, Feb 09, 2022
Target Completion
September 29, 2024
Sun, Sep 29, 2024
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close