Construction of Flood Control (Rechanneling) Project along Sibuguey River, Purok 5, Barangay Damit, Bayog, Zamboanga del Sur
Location
Damit, Bayog, Zamboanga Del Sur
Zamboanga Peninsula
ZIP: 7000
7.806376, 122.998548
Project Cost
₱49M
₱49,000,000.0
Project Timeline
Start Date
March 21, 2024
Thu, Mar 21, 2024
Actual Start
March 21, 2024
Thu, Mar 21, 2024
Target Completion
October 30, 2024
Wed, Oct 30, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor