Construction of Flood Mitigation Structure along Tagabaka Creek, Downstream with RCBC Improvement, Butuan City, Agusan del Norte
Location
City of Butuan, Agusan Del Norte
Caraga
ZIP: 8600
8.893853, 125.556114
Project Cost
₱170M
₱173,699,926.0
Project Timeline
Start Date
May 17, 2023
Wed, May 17, 2023
Actual Start
May 17, 2023
Wed, May 17, 2023
Target Completion
May 30, 2024
Thu, May 30, 2024
Source of Fund
1 source
General Appropriations Act FY 2023