Flood Mitigation along Adlayan River Bank (Upstream) San Francisco, Agusan Del Sur
Location
San Francisco, Agusan Del Sur
Caraga
ZIP: 8501
8.511440, 125.971380
Project Cost
₱49M
₱48,999,991.43
Project Timeline
Start Date
May 15, 2023
Mon, May 15, 2023
Actual Start
May 15, 2023
Mon, May 15, 2023
Target Completion
March 17, 2024
Sun, Mar 17, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates