Construction of Riverbank Protection at Magsaysay Bridge, 1st Approach, Butuan City, Agusan Del Norte
Location
City of Butuan, Agusan Del Norte
Caraga
ZIP: 8600
8.949510, 125.545460
Project Cost
₱140M
₱144,749,968.1
Project Timeline
Start Date
April 19, 2023
Wed, Apr 19, 2023
Actual Start
April 19, 2023
Wed, Apr 19, 2023
Target Completion
April 27, 2024
Sat, Apr 27, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close