Construction of River Control Structure, Barangay Dugsangon, Bacuag, Surigao del Norte
Location
Dugsangon, Bacuag, Surigao Del Norte
Caraga
ZIP: 8408
9.569064, 125.628000
Project Cost
₱49M
₱48,999,993.79
Project Timeline
Start Date
March 10, 2022
Thu, Mar 10, 2022
Actual Start
March 10, 2022
Thu, Mar 10, 2022
Target Completion
November 20, 2022
Sun, Nov 20, 2022
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project