Construction of Flood Control Structure along Tagana-an River, Tagana-an, Surigao del Norte
Location
Tagana-An, Surigao Del Norte
Caraga
ZIP: 8403
9.692559, 125.581834
Project Cost
₱96M
₱96,499,662.25
Project Timeline
Start Date
May 08, 2023
Mon, May 08, 2023
Actual Start
May 08, 2023
Mon, May 08, 2023
Target Completion
November 19, 2023
Sun, Nov 19, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor