Construction of Shoreline Protection of Ten Coastal Barangays, San Agustin, Surigao Del Sur
Location
Buhisan, San Agustin, Surigao Del Sur
Caraga
ZIP: 8305
8.740300, 126.218900
Project Cost
₱96M
₱96,499,747.18
Project Timeline
Start Date
August 14, 2022
Sun, Aug 14, 2022
Actual Start
August 14, 2022
Sun, Aug 14, 2022
Target Completion
September 25, 2023
Mon, Sep 25, 2023