Construction of Bank Protection of Solibao River Protecting Solibao Bridge (Upstream), Sta. 0+000.00 - Sta. 0+090.00, Rosario, Agusan del Sur
Location
Poblacion, Rosario, Agusan Del Sur
Caraga
ZIP: 8504
8.373423, 126.006402
Project Cost
₱29M
₱29,399,995.42
Project Timeline
Start Date
July 10, 2022
Sun, Jul 10, 2022
Actual Start
July 10, 2022
Sun, Jul 10, 2022
Target Completion
March 12, 2023
Sun, Mar 12, 2023
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor