Rehabilitation of Shore Protection Structure, Barangay Poblacion 1, Burgos, Surigao del Norte
Location
Poblacion 1, Burgos, Surigao Del Norte
Caraga
ZIP: 8424
10.016510, 126.076620
Project Cost
₱48M
₱47,951,985.95
Project Timeline
Start Date
March 27, 2023
Mon, Mar 27, 2023
Actual Start
March 27, 2023
Mon, Mar 27, 2023
Target Completion
April 23, 2024
Tue, Apr 23, 2024
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close