Rehabilitation of Drainage System, Barangay Calamias and Barangay Mabini, Lipa City Batangas
Location
Calamias, City of Lipa, Batangas
CALABARZON
ZIP: 4217
13.869640, 121.147330
Project Cost
₱9.6M
₱9,603,000.0
              
                
              
              Project Timeline
            
            Start Date
April 03, 2022
Sun, Apr 03, 2022
Actual Start
April 03, 2022
Sun, Apr 03, 2022
Target Completion
August 04, 2022
Thu, Aug 04, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
                
                  
                