Rehabilitation of Drainage System, Barangay Adya and Barangay Cumba, Lipa City, Batangas
Location
Adya, City of Lipa, Batangas
CALABARZON
ZIP: 4217
13.869690, 121.147290
Project Cost
₱13M
₱13,443,880.0
Project Timeline
Start Date
April 03, 2022
Sun, Apr 03, 2022
Actual Start
April 03, 2022
Sun, Apr 03, 2022
Target Completion
August 28, 2022
Sun, Aug 28, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor