Construction/Rehabilitation of Flood Mitigation Structures protecting Public Infrastructures/ Facilities at Barangay Quezon, Lipa City, Batangas
Location
Quezon, City of Lipa, Batangas
CALABARZON
ZIP: 4217
13.889750, 121.135720
Project Cost
₱9.6M
₱9,603,000.0
              
                
              
              Project Timeline
            
            Start Date
April 03, 2022
Sun, Apr 03, 2022
Actual Start
April 03, 2022
Sun, Apr 03, 2022
Target Completion
August 04, 2022
Thu, Aug 04, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
                
                  
                
                Project Updates
                Updates
                
                  (0)
                
              
              
            No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...