Construction of Flood Control Structures along Zapote River at Barangay San Nicolas 1, Bacoor, Cavite
Location
City of Bacoor, Cavite
CALABARZON
ZIP: 4102
14.436324, 120.977679
Project Cost
₱20M
₱19,797,210.25
Project Timeline
Start Date
July 16, 2023
Sun, Jul 16, 2023
Actual Start
July 16, 2023
Sun, Jul 16, 2023
Target Completion
April 04, 2024
Thu, Apr 04, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project