Construction of Flood Mitigation Structure along Teresa River, Barangay May-Iba, Teresa, Rizal
Location
May-Iba, Teresa, Rizal
CALABARZON
ZIP: 1880
14.571900, 121.213110
Project Cost
₱92M
₱91,675,000.0
Project Timeline
Start Date
May 08, 2024
Wed, May 08, 2024
Actual Start
May 08, 2024
Wed, May 08, 2024
Target Completion
February 10, 2025
Mon, Feb 10, 2025
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor