Rehabilltation/Reconstruction of Leviste Bridge I River Revetment, Barangay Leviste, Laurel Batangas K0090+1127
Location
Laurel, Batangas
CALABARZON
ZIP: 4221
14.069757, 120.939146
Project Cost
₱7.2M
₱7,236,836.0
Project Timeline
Start Date
January 04, 2024
Thu, Jan 04, 2024
Actual Start
January 04, 2024
Thu, Jan 04, 2024
Target Completion
April 01, 2024
Mon, Apr 01, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor