Construction of River Control along Balanac River, Brgy Maulawin, Pagsanjan, Laguna
Location
Maulawin, Pagsanjan, Laguna
CALABARZON
ZIP: 4008
14.272002, 121.452616
Project Cost
₱94M
₱93,594,921.19
Project Timeline
Start Date
March 14, 2024
Thu, Mar 14, 2024
Actual Start
March 14, 2024
Thu, Mar 14, 2024
Target Completion
February 27, 2025
Thu, Feb 27, 2025
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates